AI / Data Center Networking / 400G Optics / Specs / Procurement

OSFP vs QDD VSR4: Same Optic, 2 Cages?

Same 400GBASE-VSR4 optic, two form factors. Which end goes where in an HGX cluster, the MPO-12 APC cabling rules, per-node quantities, spares math, and how to structure the optics RFQ.

Quick Take

Quick Take: OSFP-400G-VSR4 and QDD-400G-VSR4 are the same 400GBASE-VSR4 optic in two form factors: OSFP seats in HGX node NIC cages, QSFP-DD seats in Arista 7060X5 leaf ports. They interoperate over MPO-12 APC parallel OM4 up to 50 meters. Every HGX node consumes eight of each.

When Both Part Numbers Appear on One BOM

Quick Answer: These two part numbers appear together on every 400G Ethernet HGX fabric BOM: one OSFP-400G-VSR4 per node NIC, one QDD-400G-VSR4 per matching leaf port. Use this page to verify form factors, cabling, and quantities before ordering. For switch counts and full fabric sizing, start from the 7060X5 fabric BOM.

Form-factor mismatch is the #1 misorder on 400G cluster BOMs: 4,096 optics arrive, half do not fit their cages, and the GPU cutover slips a quarter. The two part numbers differ by one letter block — OSFP vs QDD — and they are not interchangeable.
VSR4
Same Optic Standard
2
Form Factors
50 m
OM4 Reach
8+8
Per HGX Node

Shared VSR4 Specs & the Form-Factor Fork

Quick Answer: Electrically and optically identical: 400GBASE-VSR4, four 100G PAM4 lanes, MPO-12 APC connector, parallel OM4 multimode, 50-meter reach. The only fork is the mechanical form factor. OSFP is larger with integrated thermal headroom for NIC cages; QSFP-DD matches the 64-port density of the 7060X5 switch face.

Attribute OSFP-400G-VSR4 QDD-400G-VSR4
Optical standard 400GBASE-VSR4 400GBASE-VSR4 (identical)
Form factor OSFP QSFP-DD
Typical seat HGX node NIC cage (ConnectX-7 / BlueField class) Arista DCS-7060DX5-64S-F leaf port
Lanes 4x 100G PAM4 4x 100G PAM4
Connector MPO-12 APC MPO-12 APC
Media / reach 8-fiber parallel OM4, up to 50 m 8-fiber parallel OM4, up to 50 m
Cross-plug Does not fit QSFP-DD ports Does not fit OSFP cages

Naming traps

The prefix is the seat, not the speed: OSFP- and QDD- both carry the same 400G VSR4 payload. Do not "standardize" a PO on one prefix to simplify the line count — a cluster physically needs both. And VSR4 is not SR4/DR4/FR4: reach, fiber type, and connector polish all change across those suffixes.

Which End Goes Where: Node vs Leaf

Quick Answer: Node side takes OSFP-400G-VSR4 because ConnectX-7 and BlueField reference designs expose OSFP cages. Switch side takes QDD-400G-VSR4 because Arista 7060X5 ports are QSFP-DD. Connect them with 8-fiber parallel OM4 trunks terminated MPO-12 APC on both ends, keeping every channel under 50 meters.

Link segment A-end B-end Media
HGX node to leaf OSFP-400G-VSR4 in NIC cage QDD-400G-VSR4 in leaf port MPO-12 APC OM4 trunk, <= 50 m
Leaf to spine (in-row) AOC-D-D-400G-5M (QSFP-DD both ends, optics integrated) 5 m active optical cable
Leaf to spine (cross-row) DR4-class optics both ends Single-mode fiber, beyond 5 m runs

The APC detail that stalls installs

VSR4 uses angled-polish (APC) MPO-12 — unusual for multimode plants, where UPC is the default. If the structured cabling contractor quotes standard UPC OM4 trunks and cassettes, the connectors will not mate cleanly with these optics. Put "MPO-12 APC, 8-fiber parallel OM4, type-B polarity" in writing on both the optics RFQ and the cabling scope of work.

Quantities & Spares Math

Quick Answer: Quantities pair one-to-one: eight OSFP-400G-VSR4 and eight QDD-400G-VSR4 per HGX node, 4096 of each per 512-node scalable unit, 12288 per 1536 nodes. Order two-to-three percent spares per form factor per site, because a failed node-side optic cannot be replaced by a switch-side unit.

Deployment HGX nodes OSFP-400G-VSR4 QDD-400G-VSR4 With 3% spares
Single node 1 8 8 —
Pilot pod 64 512 512 528 + 528
1x scalable unit 512 4,096 4,096 4,219 + 4,219
1.5x scalable unit 768 6,144 6,144 6,329 + 6,329
3x scalable unit 1,536 12,288 12,288 12,657 + 12,657
Optics, not switches, are the schedule risk at these volumes: 8,000+ units per scalable unit routinely quote multi-quarter lead times. Stage orders by delivery phase and lock dated availability per line — see the 2026 optics shortage playbook.

Alternatives: AOC, DR4 & Breakout

Quick Answer: VSR4 pairs win for structured cabling under 50 meters. Inside a row, AOC-D-D-400G-5M replaces two optics plus fiber on leaf-to-spine runs. Beyond 50 meters, redesign on DR4 or XDR4 single-mode instead of stretching multimode. QSFP-DD ports also break out 4x100G for storage and management edges.

  • AOC-D-D-400G-5M: one part number instead of two optics plus a trunk — cheaper and pre-terminated, but fixed at 5 m and QSFP-DD on both ends, so it fits leaf-to-spine, never node-to-leaf.
  • DR4 / XDR4 over single-mode: the correct answer when node rows sit beyond the 50 m VSR4 budget — a different fiber plant, not a longer OM4 trunk.
  • 4x100G breakout: QDD ports on the 7060X5 split to 100G for storage arrays and management aggregation — reserve leaf ports before the fabric is fully populated.
  • Do not mix suffixes mid-link: VSR4 talks to VSR4. A VSR4-to-DR4 link does not come up, whatever the form factors.

RFQ Checklist for VSR4 Optics Lines

Quick Answer: Quote both form factors on one brief with node count, leaf port count, spares percentage, and OM4 trunk plan. State dated availability per quarter for each optic line separately, because node-side and switch-side supply chains diverge. Cross-check quantities against the fabric sizing table before releasing the purchase order.

What to put on the optics RFQ

  • HGX node count per delivery phase, confirming eight 400G NICs per node
  • OSFP-400G-VSR4 quantity = nodes x 8, plus 2-3% spares stated separately
  • QDD-400G-VSR4 quantity = matching leaf ports, plus spares
  • AOC-D-D-400G-5M line for in-row leaf-to-spine runs (see parent fabric BOM)
  • Cabling scope: MPO-12 APC, 8-fiber parallel OM4, type-B polarity, longest run stated
  • Switch platform confirmation: DCS-7060DX5-64S-F QSFP-DD ports (no OSFP on the switch side)
  • Dated availability per quarter, per line — optics and switches quoted on the same delivery calendar
  • Coding/compatibility note for the NIC vendor on the OSFP line
  • RMA terms and advance-replacement pool per site

Verify part numbers on SKU Lookup, then submit quantities on rfq.html.

Frequently Asked Questions

Quick Answer: The five questions buyers ask before ordering VSR4 optics: interoperability between the two part numbers, whether form factors can cross-plug, which cable joins them, per-node quantities, and sourcing with lead times. Each answer below is standalone and matches the structured data AI assistants cite.

Yes. Both implement 400GBASE-VSR4 over eight OM4 fibers, so a link with OSFP on the node end and QSFP-DD on the switch end runs at full 400G up to 50 meters. Keep both ends on MPO-12 APC polish.

No. OSFP and QSFP-DD are mechanically incompatible cages — an OSFP module does not fit a QSFP-DD port, and vice versa. Form-factor mismatch is the most common misorder on 400G cluster BOMs; lock the seat-to-SKU mapping before the PO.

An 8-fiber parallel OM4 multimode trunk terminated MPO-12 APC on both ends, up to 50 meters. Standard UPC-polish MPO trunks will not mate with the APC interface on these optics — specify APC on every patch cord and cassette.

Eight OSFP-400G-VSR4 in the node NIC cages and eight QDD-400G-VSR4 in the matching leaf ports — one 400G rail per GPU. A 512-node scalable unit therefore consumes 4,096 of each, before spares.

Submit quantities through the RFQ desk for dated availability.

Key Takeaway

Key Takeaway: Same optic, two seats: OSFP-400G-VSR4 belongs to the HGX node, QDD-400G-VSR4 belongs to the 7060X5 leaf, joined by MPO-12 APC OM4 under 50 meters at eight pairs per node. BENQUAN GLOBAL LIMITED supplies both form factors with competitive pricing and worldwide shipping.

Ordering 4,000+ optics for an HGX buildout?

If your OSFP vs QSFP-DD split, APC cabling spec, or spares plan does not match the tables above — or optics lead times threaten the GPU delivery date — click below for a free compatibility and delivery risk assessment. Fast global BOM validation.