Quick Take
Quick Take: On 15 October 2026 NERC announced that its three computational-load standards, CLO-001-1, CLO-002-1 and CLO-003-1, passed final ballot and now go to its Board, then FERC. They cover sites of 50 MW or more at 100 kV or above. Sites already operating get 36 months (1,095 days) for disturbance recording.
Definition: A computational load is a site whose main electrical demand is computing, such as a data center, AI training or inference campus or crypto-mining facility. NERC's CLO standards set the rules for how such a load is studied, connected, operated and protected on the Bulk-Power System, much as generator standards already do for power plants.
Where do the NERC data center standards stand today?
Quick Answer: On 15 October 2026 the three standards passed final ballot, and NERC says they now go to its Board of Trustees for adoption and then to FERC. FERC's 16 July directive set a 31 December 2026 filing deadline, 168 days later by our arithmetic. They are not yet in force.
Based on the ETDatacenters report of 17 October 2026, the sequence is:
- 15 October: the three standards and their implementation plans passed the final stakeholder ballot.
- Next: NERC's Board of Trustees considers adoption.
- After adoption: filing with FERC for U.S. regulatory approval.
- Deadline context: FERC's directive of 16 July requires NERC to file initial computational-load standards and proposed registration criteria by 31 December 2026, which is 168 days later (our arithmetic).
Separately, NERC's board approved revisions to its Rules of Procedure on 8 October. They create two new registered entity categories, Computational Load Owner (CLO) and Computational Load Operator (CLOP). The board also authorised expedited work on a data request to support registration, pending FERC approval. In short, the standards have cleared industry voting, not regulation. Any compliance plan should treat dates and thresholds as proposed until FERC acts.
NERC's own announcement of 15 October 2026 confirms that the standards and their implementation plans passed final ballot and will be sent to the Board of Trustees for adoption, after which NERC will file them with FERC; it also says NERC will coordinate with Canadian authorities. ERCOT's 15 October 2026 update to its Large Load Working Group lists affirmative votes of 81.58% for CLO-001-1, 77.93% for CLO-002-1 and 82.40% for CLO-003-1, against a 66.67% pass line. The slide does not label the ballot round. A trade-press report attributes those three figures to the earlier initial ballot and gives 82.33%, 78.13% and 82.69% for the final ballot; we have not verified those last three on NERC's site, so use the ERCOT figures only as indicative.
Which sites do CLO-001, CLO-002 and CLO-003 apply to?
Quick Answer: Both tests must be met: total connected load of 50 MW or more, and supply through equipment tied to the Bulk-Power System at 100 kV or higher, with multi-connection sites included. A 40 MW campus on a 69 kV feed would fail both. Registration criteria are not final, so ask your transmission planner to confirm.
The proposed applicability has two tests, and a site must meet both:
- At least 50 MW of total connected load, and
- That load supplied through equipment connected to the Bulk-Power System at 100 kV or above, including sites served from multiple points of connection.
A 40 MW campus on a 69 kV feed, for example, would not meet either test as described in the report. A 60 MW campus served at 230 kV would meet both. These two examples are our illustrations of the stated thresholds, not NERC text. Registration criteria are still being finalised, so confirm applicability with your transmission planner.
What does each standard require?
Quick Answer: CLO-001-1 covers interconnection studies and modeling data, including tripping, ride-through and recovery. CLO-002-1 covers operational data and following grid operators' instructions. CLO-003-1 covers protection-setting coordination and disturbance recording. The summary comes from press reporting; the standard text was not reviewed.
| Standard | Topic | Main requirement (per the report) |
|---|---|---|
| CLO-001-1 | Interconnection studies and modeling | Coordinated studies, commissioning procedures and planning-model data, including equipment tripping, ride-through capability and recovery after disturbances |
| CLO-002-1 | Operational data and communications | Data and communications links with grid entities; operators must follow instructions from the transmission operator, balancing authority or reliability coordinator unless physically impossible or unsafe or unlawful |
| CLO-003-1 | Protection coordination and disturbance monitoring | Processes to develop and coordinate protection-system settings across entities, and recording of electrical disturbances |
The package also revises two existing facility-interconnection standards. The report does not give the full text of any requirement, so the table is a summary and not a compliance reference.
What are the transition periods?
Quick Answer: Transition periods run from 3 months (about 91 days) to 36 months (1,095 days) after the effective date. The 36 months apply only to disturbance recording at sites already operating under CLO-003-1. Other obligations have 9-month or 12-month periods, and effective dates still depend on adoption and FERC approval.
Each standard has its own implementation plan. Figures from the report:
| Item | Transition period |
|---|---|
| CLO-001-1: planning coordinators define qualified changes | 3 months (about 91 days) after the effective date |
| CLO-001-1: interconnection study and commissioning obligations | 9 months (about 274 days) |
| CLO-002-1: data, communications and operating-instruction requirements | Generally 12 months (365 days) |
| CLO-003-1: protection-coordination requirements | Begin after 9 months (about 274 days) |
| CLO-003-1: disturbance recording for sites already operating at the effective date | 36 months (3 years, 1,095 days) |
The 36-month (1,095-day) figure applies to disturbance-recording requirements in CLO-003-1 only. It is not a general three-year grace period for every obligation, which is a common misreading. The effective dates themselves depend on adoption and FERC approval, so a calendar deadline cannot be calculated yet.
Which equipment decisions does this touch?
Quick Answer: Likely touch points are documented ride-through and tripping behavior of UPS and facility controls, protection-setting files from switchgear and relay makers, recorder and metering readiness for disturbance records, and the ability to act on grid operator instructions. These are our reading, not standard text.
NERC's requirements are about data and behavior, not about brands. For procurement, the likely touch points are:
- Ride-through and tripping behavior: CLO-001-1 asks for modeling data on how equipment trips and recovers. UPS systems, power supplies and facility controls will need documented behavior.
- Protection settings: CLO-003-1 requires a process to coordinate settings. Ask vendors of switchgear and protection relays for setting files and coordination support.
- Disturbance recording: Sites already operating have 36 months to record disturbances. Check whether existing metering and recorders have the resolution and time synchronisation needed. The report does not define a specification.
- Operational control: CLO-002-1 means the site must be able to act on operator instructions. Confirm that the facility can actually curtail or shift load in the time a grid entity may request, which the report does not specify.
These are our reading of how the standards map to equipment. We have not seen the standard text. Treat them as questions for the design team.
What does a realistic scenario look like?
Quick Answer: In an illustrative case, a campus starts at 40 MW on a 69 kV feed and later reaches 60 MW at 230 kV. The first phase fails both tests and the second meets them, so the operator asks its transmission planner about study status now and adds ride-through and protection questions to vendor questionnaires.
Illustrative example: an operator plans a campus in phases, starting at 40 MW on a 69 kV feed, with a later phase reaching 60 MW at 230 kV. The first phase fails both tests, but the second would meet them. The operator asks its transmission planner about study status now, and adds ride-through, protection and recording questions to its UPS and relay questionnaires.
Who is this for, and who is it not for?
Quick Answer: It suits owners and operators of campuses at 50 MW or more on 100 kV or higher connections, plus EPC firms and equipment vendors asked for modeling data. It does not suit sites below those thresholds, buyers outside North America, or anyone seeking final compliance dates before FERC acts.
Useful for:
- Owners and operators of campuses at or above 50 MW on a 100 kV or higher connection
- EPC firms, integrators and equipment vendors who will be asked for modeling and protection data
- Buyers planning phased AI campuses that may cross 50 MW
Not directly for:
- Sites below 50 MW or served below 100 kV, which are outside the proposed applicability
- Buyers outside North America, who are subject to different grid codes
- Anyone looking for final compliance dates, because those depend on FERC action
How to prepare an RFQ for a site that may be in scope
Quick Answer: Work out total connected load and connection voltage, ask the transmission planner about study status, and add ride-through, protection and recording questions to vendor questionnaires. Show cost impact separately as an industry estimate pending confirmation, and recheck the standards after Board adoption and again after FERC action.
- Work out the site's total connected load and the voltage of every point of connection. If either could cross 50 MW or 100 kV during phased growth, assume it is in scope.
- Ask the transmission planner for the current interconnection study status and any modeling data request.
- Add ride-through, tripping and recovery data to the vendor questionnaire for UPS, power distribution and cooling controls.
- Add protection-setting and disturbance-recording requirements to the specification of relays and metering.
- Record the budget impact separately and mark it "industry estimate, to be confirmed" until the standards are final.
- Re-check the standards' status after NERC board adoption and again after FERC action.
Frequently Asked Questions
Not yet. They passed the final stakeholder ballot on 15 October 2026. They still go to NERC's Board of Trustees for adoption and then to FERC for approval.
Sites with at least 50 MW of total connected load supplied through equipment connected to the Bulk-Power System at 100 kV or above, including sites with several points of connection.
Yes, for one requirement. Sites already operating when the standard takes effect have 36 months to meet CLO-003-1 disturbance-recording requirements. Other obligations have shorter periods, such as 9 or 12 months.
Yes. The report says the standards cover qualifying data centers, AI facilities and cryptocurrency operations, all defined as computational load.
Key Takeaway
Key Takeaway: The NERC computational-load standards cleared final ballot but are not yet adopted or approved, so treat thresholds and dates as proposed. If your site may reach 50 MW at 100 kV, start collecting equipment behavior and protection data now, and remember the 36-month (1,095-day) window covers only disturbance recording.
References
Quick Answer: NERC facts trace to NERC's 15 October 2026 announcement and the ETDatacenters report. The ERCOT slides supply the vote shares, but they do not label the ballot round. The standards still await NERC Board adoption and FERC approval, and the standard text itself was not reviewed. NERC and FERC links are the authoritative sites.
- NERC: Computational Loads Standards Pass Final Ballot, Advance to Board Adoption (15 Oct 2026)
- ERCOT: NERC Computational Load Update for the Large Load Working Group (15 Oct 2026 slides)
- ETDatacenters: NERC passes grid reliability standards for data centers, AI facilities (17 Oct 2026)
- North American Electric Reliability Corporation (NERC)
- Federal Energy Regulatory Commission (FERC)
- Open Compute Project Foundation