Quick Take
Quick Take: An HGX H200 8-GPU quote is complete only when it names twelve lines: baseboard and SKU, CPU, system memory, NVMe, network, power, cooling, software, warranty, acceptance tests, delivery terms, and price validity. NVIDIA publishes 141GB HBM3e per GPU and 1.1TB per board; every other line comes from the OEM datasheet.
Why does an 8-GPU HGX H200 quote need twelve separate lines?
Quick Answer: Because the GPU baseboard is only one part of the price. An HGX H200 8-GPU server also carries CPUs, memory, drives, network cards, power supplies, cooling and software, and each one can be swapped by an OEM. A twelve-line RFQ makes every supplier answer the same questions, so quotes can be compared.
An HGX H200 8-GPU system is a server built around an NVIDIA baseboard that holds eight H200 SXM GPUs linked by NVSwitch. NVIDIA defines the baseboard. The server maker chooses everything around it. That is where two quotes with the same headline GPU count drift apart.
Typical scenario: a systems integrator is writing a tender BOM for one training node and has three supplier replies. One lists "8x H200" and a price. Another lists CPUs, NICs and a three-year warranty. The first reply is not wrong, it is incomplete. The twelve lines below turn "8x H200" into something you can score line by line.
Fit: buyers who need a written RFQ for new 8-GPU HGX H200 servers. Not a fit: single-GPU workstations, PCIe-card servers (see the H200 NVL comparison linked in the related section), or used-crate deals without serial numbers.
What does NVIDIA publish for the HGX H200 8-GPU baseboard?
Quick Answer: NVIDIA lists eight H200 SXM GPUs per board, 141GB of HBM3e per GPU at 4.8TB/s, about 1.1TB of GPU memory per board, and third-generation NVSwitch with 900GB/s GPU-to-GPU bandwidth. Each SXM GPU has a configurable maximum power of up to 700W. Anything beyond these figures belongs to the OEM datasheet.
| Item | NVIDIA published value | Source (checked 2026-10-15) |
|---|---|---|
| GPUs per board | 8x H200 SXM (4-GPU boards also exist) | NVIDIA HGX H200 datasheet / NVIDIA H200 page |
| Memory per GPU | 141GB HBM3e at 4.8TB/s | NVIDIA H200 page |
| Memory per 8-GPU board | 1.1TB HBM3e (1,128GB class) | NVIDIA HGX reference architecture |
| FP8 Tensor Core (with sparsity) | 32 petaFLOPS per 8-GPU board | NVIDIA newsroom / datasheet |
| GPU-to-GPU fabric | NVSwitch 3rd gen, 900GB/s GPU-to-GPU, 7.2TB/s aggregate | NVIDIA HGX reference architecture |
| Max GPU power (TDP) | Up to 700W per SXM GPU, configurable | NVIDIA H200 page |
| Network options on the platform | Up to 400Gb/s with Quantum-2 InfiniBand or Spectrum-X Ethernet; BlueField-3 DPU option | NVIDIA HGX datasheet |
NVIDIA labels some figures "preliminary, subject to change", so re-check the live NVIDIA page on the day you issue the RFQ. This page does not state server weight, rack power or price, because NVIDIA does not publish them for the baseboard. Those come from the OEM.
Which 12 lines belong in an HGX H200 8-GPU RFQ?
Quick Answer: Write one line each for platform and SKU, CPU, system memory, local NVMe, network, power supplies, cooling, software, warranty and RMA, acceptance tests, delivery terms, and price validity. Mark every figure you cannot source as pending confirmation. Suppliers then answer line by line instead of quoting a single bundled number.
| # | RFQ line | What to write | Risk if skipped |
|---|---|---|---|
| 1 | Platform and SKU | "NVIDIA HGX H200 8-GPU, 8x H200 SXM" plus the OEM model name and part number | A 4-GPU board or a different GPU generation is quoted as "HGX" |
| 2 | GPU memory | 141GB HBM3e per GPU, 1.1TB per board, as NVIDIA states | Mixed-memory GPUs slip in |
| 3 | CPU | Socket count, model, core count, per the OEM datasheet | Weaker CPUs starve the GPUs during data loading |
| 4 | System memory | DIMM type, capacity, populated slots, from the OEM datasheet | Capacity met with fewer, larger DIMMs and lower bandwidth |
| 5 | Local NVMe | Drive count, capacity, interface, endurance class | Boot and scratch space is an afterthought |
| 6 | Network | Compute-fabric NIC speed and count, DPU if wanted, management port | Fabric cards missing, cluster cannot scale out |
| 7 | Power supplies | PSU wattage, count, redundancy mode, input voltage | Node trips a breaker or runs without redundancy |
| 8 | Cooling | Air or liquid, and any rack-side kit as a separate line | Cooling hardware is excluded from the quote |
| 9 | Software | OS image, driver version, NVIDIA AI Enterprise yes/no (add-on on SXM) | Licensing surfaces after delivery |
| 10 | Warranty and RMA | Term in years, response level, who handles GPU RMA, Field Diagnostic access | RMA stalls without the right diagnostic package |
| 11 | Acceptance tests | Tests, pass criteria and duration, agreed before shipment | No agreed way to reject a weak node |
| 12 | Delivery and price validity | Destination, Incoterm, lead time in days, quote expiry date; price as industry estimate / pending confirmation | Reprice-before-ship surprises |
Lines 1 to 2 are fixed by NVIDIA. Lines 3 to 10 are OEM-specific, so ask for the datasheet page behind each answer. Lines 11 to 12 are commercial and are yours to define.
How do you check power and cooling before the quote is signed?
Quick Answer: Start from the GPU figure NVIDIA publishes: up to 700W per H200 SXM GPU, so eight GPUs can reach 5,600W before CPUs, fans, drives and network cards are counted. That is arithmetic, not a server rating. Ask the OEM for the full node power figure and match it to your rack feed.
The sum 8 x 700W = 5,600W is a floor for the GPU subsystem at maximum configurable power, not the draw of the whole node. The OEM datasheet gives the system figure, PSU count and redundancy mode. For the facility side of the brief, read the sequence in our AI server power budget RFQ checklist: feeder quota first, then PDU and UPS, then cooling, then GPU nodes.
Two questions to put in writing: does the quoted PSU set keep the node running if one supply fails, and is any rack-side cooling kit a separate line item? If the answer to either is "pending confirmation", say so on line 7 or 8 instead of leaving it blank.
How do you issue the RFQ in five steps?
Quick Answer: Fix the platform first, collect the OEM datasheet for each supplier, fill the twelve lines in one shared sheet, agree acceptance tests, then send the sheet through the RFQ form with quantity and destination. Each step below names what to attach so replies arrive comparable rather than as free-form emails.
- Step 1 — Fix the platform. Write "HGX H200 8-GPU, 8x H200 SXM" and decide whether a 4-GPU board would also be acceptable.
- Step 2 — Ask for the datasheet. Require the OEM datasheet page number behind lines 3 to 8, so each figure can be traced.
- Step 3 — Fill the twelve lines in one sheet. Use the table above, one row per line, one column per supplier. Leave blanks as blanks.
- Step 4 — Agree acceptance before shipment. Pick the tests from our GPU acceptance testing guide (for example
dcgmi diag -r 3, nvbandwidth, nccl-tests) and write the pass criteria into line 11. Treat criteria as pending confirmation against the OEM spec. - Step 5 — Send it. Submit the sheet on the RFQ page with quantity, destination country and required delivery window. You can also use SKU Lookup for any catalog part numbers.
Which buyer scenarios fit this RFQ?
Quick Answer: Three scenarios fit: an integrator writing a tender BOM, an enterprise AI team replacing an older GPU node, and a data center operator comparing two OEM replies. In each case the twelve lines act as the scoring sheet. All three are typical scenarios, not named customers, and none implies a quoted price.
| Scenario (typical) | Primary line to lock | What to compare between replies |
|---|---|---|
| Integrator writing a tender BOM | Lines 1, 10, 12 | SKU, warranty path, quote validity |
| AI team replacing an older node | Lines 6, 9 | Network cards, driver and software image |
| Operator comparing two OEM replies | Lines 7, 8, 11 | PSU redundancy, cooling kit, acceptance tests |
If your project is still deciding between SXM and PCIe-card servers, settle that first, then return to this list.
What are the most common mistakes in an H200 server quote?
Quick Answer: The costly ones are quoting a 4-GPU board as an 8-GPU system, omitting cooling or network cards, leaving warranty terms unwritten, and accepting a price with no expiry date. Each mistake is cheap to catch at RFQ time and expensive to fix after delivery, which is why they sit in the table above.
- Reading "HGX H200" as proof of eight GPUs. NVIDIA sells 4-GPU and 8-GPU boards, so the GPU count must be written out.
- Treating the GPU TDP as the node power rating. The OEM figure is what your PDU must support.
- Skipping line 10. RMA for NVIDIA GPUs normally needs Field Diagnostic output, which depends on the OEM package.
- Accepting a lead time given as "ex-stock" with no number of days. Write the days, and mark them pending confirmation until the supplier signs.
- Quoting a price without an expiry date. Price is an industry estimate until confirmed in writing.
Export-control and destination screening can apply to GPU servers. State the destination and end use on the RFQ and take legal advice where unsure; this page is not legal advice.
Frequently Asked Questions
Twelve is a practical minimum: platform and SKU, GPU memory, CPU, system memory, local NVMe, network, power supplies, cooling, software, warranty and RMA, acceptance tests, and delivery with price validity. More lines are fine; fewer lets suppliers hide differences.
No. NVIDIA lists both 4-GPU and 8-GPU HGX H200 boards. The 8-GPU board adds NVSwitch for 900GB/s GPU-to-GPU bandwidth, while the 4-GPU board does not use NVSwitch. Write the GPU count explicitly on line 1.
NVIDIA states up to 700W per H200 SXM GPU, configurable, so eight GPUs reach 5,600W before other components. The full node rating comes only from the OEM datasheet. Treat any figure not on a datasheet as pending confirmation.
Put a target or budget only as an industry estimate, and expect the supplier price to be pending confirmation until quoted in writing with an expiry date. Do not use list prices from the web as a contract basis.
Use the RFQ page on benquan.hk with quantity, destination and delivery window attached. Add the filled twelve-line sheet so each line can be answered, and mark unknown items as pending confirmation.
References
Quick Answer: The figures on this page come from four NVIDIA pages: the H200 product page, the HGX reference architecture, the NVIDIA newsroom announcement, and the DCGM diagnostics guide. Each link is public and was checked on 2026-10-15. Re-open them on the day you issue the RFQ, because NVIDIA marks some values as preliminary.
- NVIDIA H200 GPU product page — 141GB HBM3e, 4.8TB/s, up to 700W SXM. Checked 2026-10-15.
- NVIDIA HGX AI Factory reference architecture: components — 1.1TB per 8-GPU node, NVSwitch 900GB/s, 7.2TB/s aggregate. Checked 2026-10-15.
- NVIDIA newsroom: HGX H200 announcement — Four- and eight-way HGX H200 boards; 32 petaFLOPS FP8 and 1.1TB for eight-way. Checked 2026-10-15.
- NVIDIA DCGM diagnostics user guide — Diagnostic levels used for acceptance testing. Checked 2026-10-15.
Key Takeaway
Key Takeaway: Write the twelve lines before you ask for a price: platform, memory, CPU, drives, network, power, cooling, software, warranty, tests, delivery and validity. Anything not on an NVIDIA or OEM datasheet stays pending confirmation. BENQUAN GLOBAL LIMITED supplies HGX H200 8-GPU systems sourced through authorized channels, with pricing pending confirmation.