GPU Acceptance · Stress Tools

Does a DCGM pass authorize the GPU RMA?

Five-tool panorama for worldwide GPU delivery evidence versus RMA authority. Marker: gpu-stress-dcgm-fieldiag-20260919.

Quick Take

Quick Take: Pick tools by job. DCGM via dcgmi diag is the in-OS health ruler; nvbandwidth measures link copy speed; nccl-tests measures training-like collectives; gpu-burn proves full-load soak. NVIDIA Field Diagnostic plus fieldiag.log with ECC enabled is the RMA authority. DCGM Pass or Fail does not determine RMA eligibility. Fit for HGX and B300-class worldwide delivery.

Key extractable numbers

GPU delivery tool map on this page: five complementary instruments—DCGM (dcgmi diag) for in-OS health, nvbandwidth for memcpy bandwidth, nccl-tests for training-like collectives, gpu-burn for thermal/power soak, and NVIDIA Field Diagnostic + fieldiag.log with ECC enabled as the RMA authority. DCGM Pass/Fail does not decide RMA eligibility. Fit framing: HGX and B300-class worldwide delivery; deep nvbandwidth CLI lives on the sibling acceptance guide.

Buyers searching for GPU stress test tools, how to accept a GPU server, or DCGM versus Field Diagnostic need a selection matrix, not a single green screenshot. This page is the panorama: which tool, when, and in what order for delivery versus RMA. Deep nvbandwidth CLI lives on the sibling acceptance guide. B300 phase playbooks live on the B300 acceptance pages. Official CLI and policy come from NVIDIA docs and GitHub READMEs retrieved 2026-09-19—not from channel blogs that still quote a 256 MiB nvbandwidth default or a -j flag on that binary.

Five-tool GPU stress stack: DCGM triage, nvbandwidth links, nccl-tests collectives, gpu-burn soak, Field Diagnostic RMA
Delivery uses the first four tools in sequence. RMA authority is NVIDIA Field Diagnostic with ECC on and fieldiag.log attached.

What is the five-tool GPU stress stack?

Quick Answer: Five complementary instruments cover GPU server delivery: DCGM for in-OS health, nvbandwidth for memcpy bandwidth, nccl-tests for training-like collectives, gpu-burn for thermal and power soak, and NVIDIA Field Diagnostic for hardware RMA evidence. Fit for HGX and B300-class worldwide acceptance. Unfit as a price quote or as treating a DCGM green run as an RMA ticket.

Definition: The GPU server stress-test stack is five complementary tools: DCGM (dcgmi) for in-OS health and diagnostics, nvbandwidth for memcpy and link bandwidth, nccl-tests for training-like collectives, gpu-burn for sustained thermal and power soak, and NVIDIA Field Diagnostic (fieldiag) for authoritative hardware and RMA evidence.

Fit: GPU server / HGX / B300-class delivery acceptance, fleet inspect, fabric versus HBM versus thermal isolation, and assembling an RMA evidence pack.

Unfit: quoting GPU prices from this page; using gpu-burn or DCGM Pass as Field Diagnostic; treating worked-example B300 numbers as your chassis SLA; running Field Diagnostic with ECC off; failing a dual-socket box solely because SYS P2P is PCIe-class; skipping nccl-tests on a training cluster purchase order.

ToolRoleTypical outputTypical runtime classAuthority
DCGM / dcgmiIn-OS health, ECC, memory, PCIe, compute pluginsPass / Fail / Warn / Skipminutes (level 1–3); hours possible at level 4Not RMA eligibility
nvbandwidthHBM / PCIe / P2P memcpy bandwidth (CE or SM)GB/s (or TB/s) matrix~1–2 min default; longer with -b 2048 -i 10Link/path evidence
nccl-testsCollectives closest to training (all_reduce_perf, …)algbw / busbw, wrong countminutes (single node); longer multi-node MPIFabric + NCCL config
gpu-burnFull-load soak (power, thermal, compute errors)errors, Gflop/s, temps15–30 min daily; 12–24 h strict deliveryFacility + stability — not RMA
NVIDIA Field Diagnostic (fieldiag)Offline/comprehensive HW diagnosticPass/Fail + fieldiag.logOEM package; industry estimate ~2 h (L1) / ~4.5–5.5 h (L2) — pending confirmationAuthoritative for RMA

nvbandwidth measures how fast the links copy. nccl-tests measures how fast training-like collectives move. gpu-burn measures whether full load holds. Field Diagnostic is the RMA authority. DCGM is the in-OS triage ruler. Delivery that skips any of the first four is incomplete. RMA without fieldiag.log is incomplete.

How do I choose a tool by goal and scenario?

Quick Answer: Start with the buyer goal, then pick the first instrument. Fast health uses dcgmi diag. HBM or PCIe questions use nvbandwidth. Training fabric uses nccl-tests. Hall power and cooling use gpu-burn. An RMA packet requires Field Diagnostic plus fieldiag.log with ECC enabled. DCGM and gpu-burn stay supporting evidence on that ticket.

Buyer goalFirst toolWhy
Fast health / is this GPU sick?dcgmi diag (level 1 quick, then 3 long)One run covers software plus memory/PCIe (L2+) plus compute/stress (L3)
Is HBM bandwidth enough?nvbandwidth D2D CE (-l for exact test name)Compare to ~80% of class peak
Is PCIe Gen5 x16 healthy?nvbandwidth H2D/D2H CEUnidirectional class bar ≥ ~50 GB/s (worked example)
Multi-GPU NVLink / P2Pnvbandwidth P2P SM and nccl-testsNV18 vs SYS topology first (nvidia-smi topo -m)
Training-like collectivesnccl-tests all_reduce_perfClosest to real train traffic
Facility PDU / cooling / soakgpu-burn (8-GPU full load)errors=0, temp class <90 °C (worked example)
RMA packetField Diagnostic + fieldiag.log (+ bug report)DCGM/gpu-burn are supporting evidence only
ScenarioRecommended sequence
New-box deliveryBaseline nvidia-smi/topo → DCGM L2/L3 → nvbandwidth (CE+SM) → nccl-tests → gpu-burn 12–24 h → Field Diagnostic if OEM package available / RMA risk high
Fault triagedcgmi diag → targeted plugin (ECC/memory, PCIe, nvbandwidth) → cross-slot if it follows the card
Daily inspectdcgmi diag -r 1 (quick) + default ./nvbandwidth
RMAField Diagnostic with ECC enabled; attach fieldiag.log; DCGM JSON is extra, not a substitute
Hall power/cooling sign-offgpu-burn all GPUs; watch PDU / CDU / inlet

Do not collapse this panorama into the sibling nvbandwidth CLI article or the B300 soak playbook. Those pages deepen one instrument. This page owns the tool-choice matrix and the Field Diagnostic equals RMA authority rule.

What does DCGM / dcgmi diag actually prove?

Quick Answer: dcgmi diag runs NVIDIA Data Center GPU Manager diagnostics in the operating system. Levels 1 through 4 add software, memory, PCIe, compute, nvbandwidth, and nccl_tests plugins. Official docs state diagnostics do not repair faults, do not replace Field Diagnostics, and do not determine RMA eligibility. Treat Skip as not a clean green.

Official user guide: DCGM Diagnostics and the dcgmi diag CLI reference. Result tokens are Pass, Fail, Skip, and Warning. Skip often means a known issue caused the test to be skipped—treat it as not signed off.

SelectorSuiteAdds (class)
1 / quick / shortQuickSoftware deployment checks
2 / mediumMediummemory + pcie
3 / longLongdiagnostic, memory_bandwidth, targeted stress/power, nvbandwidth plugin, nccl_tests plugin (when present)
4 / xlongExtra longmemtest + pulse_test on top of L3

Example commands (keep exact flags):

dcgmi discovery -l dcgmi diag -r 1 dcgmi diag -r 3 dcgmi diag -r memory -i <GPU_INDEX> dcgmi diag -r 2 -t pcie dcgmi diag -r 1 -j dcgmi dmon -i 0 -e 203 dcgmi health -g 1 dcgmi topo -g 1

Official caveat (must teach): DCGM Diagnostics do not repair faults, do not replace NVIDIA Field Diagnostics, and do not determine RMA eligibility. A Fail can be host, driver, cooling, power, or interference—not only the GPU ASIC. Save JSON with DCGM’s own -j flag. That is not the same as nvbandwidth’s --format json.

If dcgmi diag -r nvbandwidth fails, first check that the nvbandwidth binary is installed and that GPUs are idle (is_allowed / MCUTIL). Plugin absence is a host packaging issue, not proof the SXM needs RMA.

When should I run nvbandwidth vs nccl-tests?

Quick Answer: Run nvbandwidth to score HBM D2D, PCIe H2D/D2H, and P2P copy paths with Copy Engine and SM kernels. Run nccl-tests when the purchase order is training fabric: all_reduce_perf is closest to real collectives. GitHub nvbandwidth defaults are 512 MiB and three samples; export with --format json, not a blog -j flag.

NVIDIA nvbandwidth needs CUDA 11.x+ (multinode 12.3+ and driver 550+) and CMake 3.20+. Default buffer is 512 MiB (-b); default iterations are 3 (-i). Always list tests with -l before freezing -t names. Strict acceptance often uses -b 2048 -i 10 --format json. Channel posts that still say 256 MiB or -j on this binary are stale.

  • Copy Engine (CE): hardware DMA; does not consume SM compute; measures link ceiling.
  • Streaming Multiprocessor (SM): kernel copy; closer to application memcpy cost.
  • Acceptance rule: run both CE and SM where the family exists. Path families on this page: D2D / H2D / D2H / P2P. Full CLI appendix is the sibling nvbandwidth article.

nccl-tests and the NCCL product page cover collectives: all_reduce_perf (most used), all_gather_perf, alltoall_perf, broadcast_perf, reduce_perf, reduce_scatter_perf, sendrecv_perf.

./build/all_reduce_perf -b 8 -e 128M -f 2 -g 8

Read algbw (algorithm bandwidth), busbw (bus bandwidth), and wrong—which must stay 0. Watch peak as message size grows; too-small messages never hit the fabric ceiling. Multi-node MPI with InfiniBand GID, traffic class, or QPS knobs is a site-specific pattern pending confirmation against your fabric—not a copy-paste for every hall.

Topology lesson: same-socket NV18 pairs should land in the high band. Cross-CPU SYS pairs that walk PCIe are expected near PCIe class. That low SYS cell is not a broken NVLink unless an expected NV18 cell collapses to SYS-class numbers. Confirm with nvidia-smi topo -m.

When is gpu-burn the right soak — and when is it unsafe?

Quick Answer: gpu-burn is the community full-load soak for PDU, cooling, and compute stability. Daily smoke is 15–30 minutes; strict delivery is 12–24 hours with errors equal to zero. It is not NVIDIA Field Diagnostic and does not determine RMA. Watch temperatures and facility power; a multi-GPU step can trip PDU or OPP protection.

Repo: wilicc/gpu-burn (community; not NVIDIA Field Diagnostic).

git clone https://github.com/wilicc/gpu-burn.git cd gpu-burn && make ./gpu_burn 1800 ./gpu_burn -d 3600 ./gpu_burn 7200

Read load percent, Gflop/s versus class peak, errors must be 0, and temperatures. A worked-example class watches ≥90 °C as “check fans and air path immediately”—pending confirmation versus the OEM thermal spec. Keep a second terminal on watch -n 1 nvidia-smi. Daily inspect can stay 15–30 minutes. Strict new-box delivery should hold 12–24 hours with no errors.

Unsafe or incomplete: using a two-hour error burst as the NVIDIA RMA packet; running all eight GPUs on an undersized PDU without watching CDU inlet; skipping DCGM and nvbandwidth and calling soak “acceptance.” Facility faults show up here first. Hardware RMA still needs Field Diagnostic.

Optional host supplement after the GPU stack (not a sixth equal tool): stress-ng --vm $(nproc) --vm-bytes 90% --timeout 2h --metrics-brief or memtester for DRAM, and stress-ng --cpu $(nproc) --timeout 30m plus turbostat for CPU throttle class. Pass narrative is no new DRAM ECC and CPU holding base clocks—pending confirmation versus OEM.

Is NVIDIA Field Diagnostic required for GPU RMA?

Quick Answer: Yes for an NVIDIA-class RMA packet. Field Diagnostic (fieldiag) is the authoritative hardware tool and is usually required before RMA. ECC must be enabled. Attach fieldiag.log. Obtain the OEM or NVIDIA support package—this is not a public GitHub clone like gpu-burn. DCGM JSON is extra evidence, never the ticket.

Official names: NVIDIA Field Diagnostic / HW Field Diag. Docs: HW Field Diag, RMA Process, and GPU Debug Guidelines (“authoritative… usually required before an RMA”; contact your system vendor for if/when/how).

Policy (Track 1)Value
Binary./fieldiag (OEM packages may wrap fieldiag.sh --level1/--level2/--sit)
ECCMust be enabled. Failures only with ECC off are not RMA-eligible (NVIDIA RMA Process)
Artifactfieldiag.log with the RMA request (missing log delays the ticket)
Pass meaningHardware in good condition → look at software/app; NVIDIA may still want “failure follows the board” evidence
ObtainOEM / NVIDIA support package — not a public GitHub clone. HGX SKUs often have SKU-specific packages

Module runtimes such as connectivity / gpumem / cudacores / pcie / nvlink / gpustress / power / thermal, and wrappers such as --sit ~34 min / --level1 ~2h09 / --level2 ~4h25, are OEM-package class / pending confirmation versus your Field Diagnostic package. USB boot flows that mention Rufus and /var/diags are one OEM narrative, not universal—follow the Field Diagnostic Quick Start in your package (DU-05711-001 / DU-05363-001 class docs).

Channel stories about error strings such as “540 NVRM Fatal error”, “140 NvLink bus error”, “143 PCI Express bus error”, or “PEX ERROR” are pending confirmation against your OEM fieldiag log decoder. Do not treat them as a public NVIDIA error catalog on this page.

B300 worked-example pass bars (simulated)

Quick Answer: These B300-class 8-GPU dual-socket bars are an illustrative simulation pending confirmation against your OEM datasheet and purchase order. Use them to shape RFQ language. HBM D2D CE targets about 80 percent of class peak; Gen5 x16 H2D CE targets about 50 GB/s unidirectional; NV18 P2P SM sits far above SYS-class cross-CPU cells.

Industry estimate / pending confirmation: every Theory, Pass bar, and runtime class in this section is a worked example for an illustrative B300 8-GPU dual-socket topology. Do not treat these figures as a guarantee for your purchase order.

MetricToolTheory classExample pass barFirst checks if low
HBM D2Dnvbandwidth CE~8 TB/s≥ ~80% (≥ ~6.4 TB/s)clocks, thermal, HBM
PCIe H2D / D2Hnvbandwidth CEGen5 x16 ~64 GB/sunidirectional ≥ ~50 GB/sGen/Width, slot, affinity
PCIe bidirectionalnvbandwidth CE~40–55 GB/s class totaldo not treat half-duplex split as failsame
NVLink P2Pnvbandwidth SMNV18 bidir ~900 GB/s class~800–900 GB/s classBridge, topo -m, nvlink -s
Cross-CPU SYSnvbandwidth~50 GB/s PCIe classexpected low — not an NV18 failtopology matrix
Collectivesnccl-testsbusbw rises with sizepeak + wrong=0NCCL/IB/topo
Soakgpu-burnerrors=0; temp class <90 °C12–24 h deliveryPDU, CDU, fans
HW / RMAfieldiagPass + logFail → OEM RMA pathECC on; cross-slot
SymptomLikely causeCheck
DCGM green, training still slowCollectives/fabric, not ASIC healthnccl-tests + nvbandwidth P2P
NV18 cell ~50 GB/sBridge / actually SYStopo -m, reseat NVLink Bridge
H2D ~30 GB/sGen4 or x8nvidia-smi -q PCIe
gpu-burn errors after 2 hthermal/power, not “needs RMA yet”CDU, fans, then Field Diag
RMA bouncedNo fieldiag.log or ECC was offRMA Process policy
dcgmi diag -r nvbandwidth Failplugin binary missing / MCUTIL>10%install nvbandwidth; idle GPUs
Fieldiag USB will not bootWrong OEM ISO / driver still loadedFollow your package QSG; unload NVIDIA module as documented

HowTo: delivery vs RMA sequence

Quick Answer: Capture nvidia-smi baselines with ECC on, triage with dcgmi diag levels 1 and 3, measure links with nvbandwidth JSON, measure collectives with all_reduce_perf, soak 12–24 hours on gpu-burn, then run OEM Field Diagnostic only if hardware remains suspect. Attach fieldiag.log. DCGM green never opens the RMA by itself.

  1. Step 1 — Capture baseline: Run nvidia-smi -q (SKU, driver, CUDA, PCIe Gen/Width, clocks/temp) plus nvidia-smi topo -m and nvidia-smi nvlink -s into a dated folder. Confirm ECC is on if RMA is in scope.
  2. Step 2 — Triage in OS: dcgmi discovery -l then dcgmi diag -r 1 (quick) and dcgmi diag -r 3 (long) on idle GPUs; save JSON (-j). Treat Skip/Fail as “not signed off”, not as an automatic RMA.
  3. Step 3 — Measure links: Build nvbandwidth from GitHub; ./nvbandwidth -l; run a default sweep plus D2D CE, H2D/D2H CE, P2P SM with -b 2048 -i 10 --format json. Score NV18 versus SYS cells (do not fail SYS-class cross-CPU as broken NVLink).
  4. Step 4 — Measure collectives: all_reduce_perf single-node (-g 8 class) then multi-node only if the purchase order is a cluster; wrong must be 0; archive busbw peaks.
  5. Step 5 — Soak the facility: gpu-burn 12–24 h for strict delivery (or 15–30 min smoke); errors=0; watch PDU/CDU/nvidia-smi. This does not replace Field Diagnostic.
  6. Step 6 — RMA packet (only if hardware still suspect): Run the OEM NVIDIA Field Diagnostic with ECC enabled; keep fieldiag.log + nvidia-bug-report.log.gz; cross-slot if the fault follows the GPU. Submit via vendor/NVIDIA — DCGM/gpu-burn logs are attachments, not the ticket.

Real-World Deployment Scenarios

Quick Answer: Map five buyer pictures before you freeze the evidence pack. New HGX nodes need the full delivery sequence. Live Xid storms start with targeted DCGM. Daily fleet inspect stays quick. Supplier bandwidth disputes need nvbandwidth JSON plus topology. Single-SXM RMA needs Field Diagnostic, not gpu-burn alone.

Scenario A: New 8× B300 HGX node (finance will not sign without bandwidth plus soak)

Workload Profile: Worldwide inbound HGX node; CapEx will not close without a written bandwidth and soak pack.

Architectural Fit: Sequence Steps 1–5. Add Field Diagnostic if the OEM USB or ISO is in the crate or RMA risk is high.

Scenario B: Training job Xid / ECC storm on one GPU in a live rack

Workload Profile: Production training interrupted on a single index while the rest of the mesh stays healthy.

Architectural Fit: DCGM targeted plugins, then nvbandwidth on that index. Field Diagnostic only after isolation and cross-slot if the fault follows the card.

Scenario C: Daily fleet inspect across 32 nodes

Workload Profile: Operations needs a cheap, repeatable health pulse without taking the cluster offline for hours.

Architectural Fit: dcgmi diag -r 1 plus default ./nvbandwidth. Escalate to level 3 only on drift versus the dated baseline.

Scenario D: Supplier dispute — demo passed versus NV18 at 50 GB/s

Workload Profile: Integrator claims the node passed a demo; buyer measures SYS-class numbers on an expected NV18 pair.

Architectural Fit: Archive nvbandwidth JSON with nvidia-smi topo -m and score against the sibling nvbandwidth article thresholds. Do not argue from gpu-burn screenshots.

Scenario E: RMA of a single SXM after soak errors

Workload Profile: gpu-burn showed errors after hours; finance wants the board swapped.

Architectural Fit: Field Diagnostic plus log plus ECC-on policy. gpu-burn errors alone are not the NVIDIA ticket.

Frequently Asked Questions

Quick Answer: DCGM triages in the OS; Field Diagnostic plus fieldiag.log with ECC on is the RMA authority. gpu-burn cannot open that ticket. New B300 boxes start with nvidia-smi then DCGM. Cross-CPU ~50 GB/s is often SYS. Training purchase orders need both nvbandwidth and nccl-tests. ECC must be enabled before fieldiag runs.

DCGM (dcgmi diag) is the in-OS health and plugin suite. NVIDIA Field Diagnostic (fieldiag) is the authoritative hardware diagnostic usually required before an RMA. A DCGM Pass or Fail does not determine RMA eligibility. Attach fieldiag.log with ECC enabled; keep DCGM JSON as supporting evidence only.

No. gpu-burn is a community soak that proves power, thermal, and compute stability. Errors equal zero after 12–24 hours is a delivery bar, not an NVIDIA ticket. Open RMA with Field Diagnostic, ECC on, and fieldiag.log. Treat gpu-burn logs as attachments after isolation.

Capture nvidia-smi baselines and topology first, then dcgmi diag level 1 quick and level 3 long on idle GPUs. Next run nvbandwidth CE and SM, nccl-tests all_reduce_perf, then gpu-burn soak. Add Field Diagnostic when the OEM package is in the crate or hardware is still suspect.

Cross-CPU pairs often walk SYS or PCIe instead of NV18. Expect roughly PCIe-class bandwidth on those cells. Fail the chassis only when an expected NV18 pair collapses to SYS-class numbers. Confirm with nvidia-smi topo -m before blaming the GPU ASIC.

Yes on a training cluster purchase order. nvbandwidth measures memcpy and link copy (CE versus SM). nccl-tests measures training-like collectives such as all_reduce_perf, where wrong must stay 0. A healthy D2D matrix can still hide fabric or NCCL configuration faults that collectives expose.

Yes. NVIDIA RMA Process requires ECC enabled. Failures that appear only with ECC off are not RMA-eligible. Keep fieldiag.log with the request. Missing the log or running Field Diagnostic with ECC disabled delays or bounces the ticket.

References

Quick Answer: Anchor every script to NVIDIA DCGM diagnostics, Field Diagnostic and RMA Process docs, plus the GitHub READMEs for nvbandwidth, nccl-tests, and gpu-burn. Prefer those pages over channel blogs for buffer defaults, JSON flags, and RMA eligibility language on this 2026 stack.

Key Takeaway

Key Takeaway: Close delivery only after DCGM long diagnostics, nvbandwidth CE/SM JSON, nccl-tests with wrong=0, and a 12–24 hour gpu-burn soak. Open RMA only with Field Diagnostic, ECC enabled, and fieldiag.log. DCGM green is triage, not eligibility. BENQUAN supplies GPU server acceptance tooling guidance with competitive pricing for B300-class worldwide delivery RFQs.

Not sure your GPU delivery vs RMA evidence pack is complete?