Quick Take
Quick Take: After OCP on 12 October 2026, do not freeze a 2026 PO on USFP or a G302 commercial-box PID. USFP is a 400Gb/s-per-lane pluggable spec (up to 12.8T). G302 is 51.2T ToR silicon with 200G SerDes and Cisco 1.6T optics. G300 is 102.4T in sampling. Keep this week's RFQ on orderable 800G / Spectrum-X / Silicon One E100 lines.
What did Cisco and NVIDIA freeze on 12 October 2026?
Quick Answer: Three identities, none of them a public commercial-box PID. USFP = planned 400G/lane module spec with NVIDIA, TE Connectivity, and Amphenol. G302 = 51.2T ToR silicon. G300 = 102.4T sampling with first systems shipping. Cisco 8001 out-of-band and P200 production are different stories.
Typical scene: a GPU fabric brief already named today's 800G OSFP ToR. Finance hears “1.6T and USFP at OCP” and asks to swap the PO this week. Treat USFP like a new tire size announced before the catalog lists that size — you still buy today's tires as their own line. That is a typical procurement trap, not a named customer.
Official Cisco newsroom language: G302 is planned to begin shipping to customers before the end of 2026. Channel notes that say early 2027 and GA still TBD stay on this page as pending confirmation. Do not pick one date and hide the other. USFP remains a specification and a forthcoming multi-source project — channel notes that it releases after 102.4T switches exist. No public USFP or G302 chassis MPN was published.
- Fit: Open 2026 AI fabric RFQs that must not grow a fake USFP or G302 box line; dual-path briefs that keep Spectrum-X / Arista 800G as a second column; worldwide BOMs that need a 1.6T plan-year field.
- Unfit: A silent substitute for N9336C-SE1; a drop-in OSFP; a Cisco 8001 management box; a P200 scale-across router RFQ.
What is orderable vs still silicon or spec?
Quick Answer: Put three columns on the RFQ: today's PID, a 1.6T plan year, and a watch-item for G302/USFP with no MPN. Do not invent a catalog code to make the spreadsheet look complete. Soft channel net is industry estimate / pending confirmation.
| Line | Official identity (12 Oct 2026) | 2026 RFQ action |
|---|---|---|
| USFP | 400Gb/s-per-lane pluggable spec; 16 lanes in OSFP-sized footprint; path to 32 lanes; up to 12.8T; ~4× bandwidth density and ~1.3× power efficiency vs 200G/lane | Spec watch-item. Not a PO line. MSP still upcoming. |
| Silicon One G302 | 51.2T ToR silicon, 200G SerDes, Cisco 1.6T optics, direct-to-chip liquid cooling; planned ship before end of 2026 | Silicon, not a commercial-box PID. Channel early-2027 / GA TBD = pending confirmation. |
| Silicon One G300 | 102.4T; customer sampling; first G300-powered systems shipping | Not an enterprise catalog SKU on this page. Do not merge with G302. |
| Today's ToR / spine | Orderable Nexus / Spectrum-X / 800G OSFP class already on the brief | Freeze PID × qty here. Worldwide shipping language is not a stock promise. |
| Silicon One E100 (N9336C-SE1) | 36×100G 1RU, different ASIC generation | Own sku-page. Do not retag as G302. |
Cisco and NVIDIA say the first planned USFP transceivers pack 16 full-duplex lanes in an OSFP-sized module for switches and SuperNICs, with a two-step insertion connector. Power dissipation is described up to 100 W without a dedicated cooling circuit inside the transceiver. That is roadmap language, not a field-replaceable SKU you can copy onto an RFQ this week.
What this page is not
Quick Answer: Not Cisco 8001 (Silicon One A100 out-of-band, 10G or 1G). Not P200 51.2T production quotes. Not Live Protect for SONiC in mid-2027. Not a G302 sku-page. Those are other H1s.
Microsoft and Alibaba Cloud statements on Silicon One P200 production sit on the Cisco newsroom. They prove P200 is in hyperscale production. They do not prove BENQUAN supplied those systems, and they do not make USFP orderable. Leave them in References.
Do not copy secondary coverage that calls G302 a “1.6T ToR.” Official math is 51.2T of switching silicon with 1.6T optics. Mixing those two numbers in one spreadsheet cell is how a 2026 CapEx pack over-buys a product that has no PID.
Typical use cases: who must act this week?
Quick Answer: Act if an open GPU-fabric RFQ is about to grow a USFP or G302 box line, or if a 1.6T upgrade year was never written. Do not wait for a catalog PID that OCP did not publish.
Integrators: dual-box still means two hardware-list bases on today's switches. USFP does not replace empty OSFP cages. Procurement: worldwide lead time on today's optics is its own field — a spec date is not a warehouse receipt. Ex-stock free-port language on this site is not a promise that USFP sits on a pallet.
- Missing plan year: fabric approved at 800G, no 1.6T year — add the year, do not invent a G302 PID.
- Swapped PO: OCP headline used to overwrite this week's 800G OSFP column — put the headline back as a watch-item.
- ASIC mix-up: N9336C-SE1 retagged as G302 because both say Silicon One — keep E100 on the SE1 page.
- Dual-path CapEx: if 2026 spend cannot wait, keep Spectrum-X / Arista 800G as a second column only.
Buyer decision matrix
Quick Answer: If the line has no public PID, it is not this week's PO. If the line is today's ToR or 800G optic, freeze quantity and support years. If the line is a 1.6T year, keep it as a date, not a SKU.
| Situation | List posture | RFQ ask |
|---|---|---|
| Quote grew a USFP line | Spec only on 12 Oct 2026 | Delete the PID-shaped cell; keep 800G OSFP |
| Quote grew a G302 box | Silicon; planned ship before end of 2026 (official) | No commercial-box MPN; flag vs early-2027 channel note |
| Need 1.6T endpoints later | Plan year, not a SKU | Year + current PID × qty |
| Open 36×100G Silicon One | N9336C-SE1 / E100 | Stay on the SE1 sku-page |
| Spectrum-X fabric already drawn | Today's NVIDIA Ethernet BOM | Keep SuperNIC / switch PIDs; USFP as interoperability watch-item |
How do you freeze a 2026 RFQ after OCP?
Quick Answer: Copy today's switch PID × qty, optics class, HA, and the 1.6T plan year. Write USFP and G302 as watch-items with the 12 October 2026 date. Do not mint a fake MPN.
- Step 1 — Name what is not a PID — USFP is a spec. G302 is silicon. Neither is a commercial-box SKU on this freeze.
- Step 2 — Lock official identities — 51.2T / 200G SerDes / 1.6T optics for G302; 102.4T sampling for G300; 400G/lane up to 12.8T for USFP.
- Step 3 — Keep today's orderable column — ToR/spine PID × qty and 800G OSFP class stay on the 2026 RFQ.
- Step 4 — Add a 1.6T plan-year column — Year only. Empty is honest. A invented G302 box code is not.
- Step 5 — Flag ship-date mismatch — Official planned before end of 2026 versus channel early 2027 / GA TBD. Pending confirmation.
- Step 6 — Dual-path only if CapEx cannot wait — Spectrum-X or Arista 800G as a second column, equal assumptions, no USFP on either side.
RFQ checklist
Quick Answer: Send today's PID × qty, HA, optics class (800G OSFP vs 1.6T plan year), and whether any draft already printed USFP or G302. Ask for orderable vs watch-item columns. No public net.
What to put on the RFQ
- Current ToR / spine PID × quantity and airflow
- Optics class already drawn (800G OSFP / QSFP-DD) — empty cages are empty
- HA count (two boxes, two bases)
- 1.6T plan year if the fabric must grow later
- Strike-through any USFP or G302 box code a workbook invented
- Support years on the orderable hardware, not on the spec
Use SKU Lookup · Cisco for codes that already exist, then submit on rfq.html. BENQUAN reviews equal AI-fabric briefs in one business day. Worldwide shipping is not a USFP stock claim. Channel net pending confirmation.
Common RFQ pitfalls after OCP 12 October 2026
Quick Answer: Buyers lose CapEx when they treat a spec as a PID, treat 51.2T silicon as a 1.6T switch, or retag E100 as G302. Keep three columns: orderable, plan year, watch-item.
- USFP on the PO: no public module MPN on 12 Oct 2026.
- G302 as 1.6T ToR: silicon is 51.2T; 1.6T is the optics class.
- G300 = G302: 102.4T sampling is not 51.2T ToR silicon.
- SE1 retag: N9336C-SE1 stays E100.
- 8001 mix-up: out-of-band A100 is a different H1.
- P200 as proof USFP ships: production quotes are P200, not USFP.
- Spec date as stock: free-port language is not a pallet of USFP. Pending confirmation.
Frequently Asked Questions
Quick Answer: USFP is not orderable. G302 is not a 1.6T switch PID. G300 is not G302. N9336C-SE1 is a different ASIC. Public pages carry no list or net.
No. On 12 October 2026 Cisco and NVIDIA announced plans for USFP — a 400Gb/s-per-lane pluggable spec, not a catalog PID. Do not write USFP as a line on this week's PO. Freeze today's OSFP/800G class instead. Channel net pending confirmation.
No. Official identity is the first 51.2T switching silicon with 200G SerDes for ToR, with Cisco 1.6T optics and direct-to-chip liquid cooling. That is silicon plus an optics class, not a 1.6T chassis PID. Do not copy secondary headlines that collapse G302 into “1.6T ToR.”
No. G300 is 102.4T, in customer sampling, with first G300-powered systems shipping. G302 is 51.2T ToR silicon planned to begin shipping to customers before the end of 2026 per the newsroom. Channel notes that say early 2027 / GA TBD stay pending confirmation beside that official sentence.
No. N9336C-SE1 is today's Silicon One E100 36×100G 1RU. G302 is a 2026 OCP silicon announcement. Keep SE1 on its own sku-page. Do not swap the ASIC name on an open 36×100G RFQ.
Quote list, net, and discount stay off public pages. No public G302/G300/USFP commercial-box PID was published on 12 October 2026. Channel figures are industry estimate / pending confirmation on the RFQ.
References
- Cisco — Advances Scalability and Openness at OCP 2026 (12 Oct 2026; fetched 2026-10-13)
- Cisco / NVIDIA — USFP pluggable optics (12 Oct 2026)
- Cisco blog — USFP path to AI connectivity (12 Oct 2026)
- NVIDIA IR — USFP form factor (12 Oct 2026)
- Cisco Silicon One architecture overview
Key Takeaway
Key Takeaway: On 12 October 2026, freeze USFP as a 400G/lane spec and G302 as 51.2T ToR silicon — not as 2026 PO lines. Keep this week's RFQ on orderable 800G / Spectrum-X / E100 PIDs, add a 1.6T plan year, and mark G302 ship dates pending confirmation. BENQUAN GLOBAL LIMITED supplies AI-fabric RFQ mapping with competitive pricing and configuration support. Confirm quantity, HA, optics class, and plan year on the same brief. Channel net pending confirmation.